We are extremely happy to report that we have received our I-956F Formal Receipt Notice today, on August 22, 2022, for the Manhattan 11th Ave Marriott Tribute Portfolio Hotel Project (11th Ave Tribute Project). As such, our investors in this project can start filing their I-526E petitions TODAY!!!
Please note that this receipt notice is currently required per USCIS guidance issued on July 12th with the newly released Form I-526E, Immigrant Petition by Regional Center Investor.
Our 11th Ave Tribute Project construction team poured the top floor (52nd) in August 2021. Currently, exterior and interior construction work are ongoing. As of June 30, 2022, 1604.42 jobs have already been created.